SUPERIOR, WI/DULUTH, MN (KDAL) – Drivers may encounter some lane and ramp closures this week as prep work continues in advance of the Blatnik Bridge replacement project.
Lane configuration and traffic signal work will be done on Belknap Street in Superior and entrance and exit lanes are being reconfigured where Highway 2 connects with I-35 and 46th Avenue West in Duluth.
Work is also continuing to resurface Winter Street and Susquehanna Avenue in Superior which will see more traffic once the Blatnik Bridge closes next spring.
Full closure of the bridge will happen no sooner than March 1st of 2027 and the new bridge should be open to traffic by October 31st of 2031.